State-run hydro power giant NHPC on Thursday said the flash flood in October 2023 at the Teesta-V power station, Sikkim resulted in a loss of Rs 1,075.97 crore.
The company further noted that three units of 250 MW each of Subansiri Lower hydro project will be completed by May, 2025 and remaining five units of 250 MW each will be completed by May, 2026.
The company in a regulatory filing said that the amount of damage caused by flash flood occurred on October 4, 2023 was to the tune of Rs 1,075.97 crore, which has been reported to the insurer.